In this Article today we will cover about the When to Start Curing of Concrete | Best Time for Concrete Curing Why Curing of Concrete is Important | Curing in Construction | Importance of Curing of Concrete | Curing Process of Concrete | Curing Period of Concrete | What is the Perfect time for Curing of Concrete | Minimum Curing Time for Cement Concrete

When to Start Curing of Concrete, Best Time for Concrete Curing, Why Curing of Concrete is Important, Curing in Construction, Importance of Curing of Concrete, Curing Process of Concrete, Curing Period of Concrete, What is the Perfect time for Curing of Concrete, Minimum Curing Time for Cement Concrete


hey guys welcome to QA QC Civil Engineering have you ever wondered when to start curing of concrete I know you did so let's discuss it

What is the Best Time for Concrete Curing?


Curing of concrete is the process of maintaining moisture inside the freshly casted concrete to continue the hydration process and to achieve the desired properties of hardened concrete.

Before starting curing concrete you should know the actual behavior of the freshly casted concrete.

Once you know and understand the behavior of concrete very well then you will get a better idea when to start curing of concrete.

When we add water and dry concrete mix, hydration of cement will start immediately and heat will be generated inside the concrete. 

Without proper hydration of cement, concrete will never gain the design strength. 

When the concrete is placed and compacted, cement slurry Rises through the surface of concrete due to the settlement of concrete.

In technical term, this phenomenon is called as "bleeding in concrete". The rate and duration of
bleeding depend on many factors i,e. mix proportion, thickness or depth of concrete, concrete compaction method, water cement ratio etc. 

There are so many factors that affect the curing of concrete. It depends on the chemical composition and find this of cementitious materials, water cement ratio mixture proportions aggregate characteristics, chemical and mineral lab mixtures added, the temperature of the concrete. During initial setting, bleed water will evaporate from the surface of the concrete.

The rate of evaporation of bleed water will depend on so many factors i.e, air temperature and relative humidity, concrete temperature, radiant energy from the direct Sun and wind velocities.

Due to above described factors concrete curing is carried out in three phases and the length of time depends on the concrete and environmental conditions. 

Here we have discussed these three stages: 

1. Initial Curing:


During the initial setting, sometimes bleed water start evaporating from the surface faster than it is rising out from the concrete. If evaporation happens faster than usual time than, the only factor that effect is the high temperature. 

When all the water gets evaporated from the surface, you need to do some initial curing to minimize the moisture loss. During this period, if you do not start the curing, it may lead to
plastic shrinkage cracks in concrete. 

The initial curing of concrete can also be done by fogging. 

2. Intermediate Curing:

Sometimes intermediate curing is necessary and is carried out when finishing is completed but before the concrete has reached its final set. During this period evaporation may need to be reduced, but the concrete is not yet be able to tolerate the direct application of water or the mechanical damage resulting from the application of plastic sheets. 

In this stage liquid forming membrane compound can be used effectively to reduce evaporation loss.

3. Final Curing:


Final Curing is carried after final finishing and after the concrete has reached its final set. Final curing can be done by application of wet covering i.e, ponding method, saturated burlap, spraying water, curing compounds etc. 

The normal final setting time of cement is six to eight hours. In short, the curing should start after minimum six hours (Final setting time of cement) and not less than 24 hours. 

Thus, when concrete curing has to start is varies and depends on when the surface of the concrete begins to dry. Concrete curing should be started before concrete surface loses its water and undergo shrinkage. This is very important for concrete with low to very low water cement ratio which does not have much water to bleed to the surface. 

that's all for today see you in the next article, thanks for reading this article please like and share on social media.

Conclusion:

Full article on When to Start Curing of Concrete | Best Time for Concrete Curing Why Curing of Concrete is Important | Curing in Construction | Importance of Curing of Concrete | Curing Process of Concrete | Curing Period of Concrete | What is the Perfect time for Curing of Concrete | Minimum Curing Time for Cement Concrete. Thank you for the full reading of this article in "QA QC Civil Engineering" platform in English. If you find this post helpful, then help others by sharing it on social media.

QA QC Civil Engineering

Hi I am a Civil Engineer by profession but I’ve specialized and taken the journey in the field of Quality Engineering, QA/QC Civil Engineering, Bar Bending Schedule, Quantity Surveying, Construction, Concrete Works, Estimating & Costing and AutoCAD Civil 3D.

Post a Comment

Please Do Not Enter any Spam Link in the Comment Box.

Previous Post Next Post