Understanding About Inspection and Test Plan (ITP) | Inspection Records | Inspection Levels

In this article today we will cover Inspection and Test Plan (ITP) | Inspection Records | Inspection Levels Checklist or QVD Quality Verifying Documents | Preparation, Review and Approval Inspection Responsibilities | Inspection Levels Surveillance | Request | Execution | Witness | Hold Point | Test | Review | Records

Inspection and Test Plan (ITP), Inspection Records, Inspection Levels, Checklist or QVD Quality Verifying Documents, Preparation, Review and Approval, Inspection Responsibilities, Inspection Levels, Surveillance, Request, Execution, Witness, Hold Point, Test, Review, Records



For each activity on a construction site, there would be a corresponding Method Statement as well as Inspection and Test Plan including Checklist shall be developed.
Here is a definition of ITP:

Inspection & Test Plan (ITP) 


An Inspection & Test Plan is the program of inspection, testing of materials, and survey shall be prepared and submitted by the contractor to the Engineer for approval before usage and application to the site.
Here is a definition of Checklist

Checklist or QVD (Quality Verifying Documents) 


A list of items shall be noted or checked in a completed activity. It is always attached to the Inspection Request. To be signed by concerns parties once the inspection is approved.

Preparation, Review and Approval

Inspection and Test Plan is made and issued by the Quality Engineer, it should then be reviewed by the Quality Manager, Construction Manager and approved by Project Manager before it shall submit to the Engineer.
As it is always required by the contract or specification, Method Statement  and Inspection and Test Plan including Checklist shall be submitted to the Engineer for approval.
The QA/QC Engineer shall maintain a register of all Inspection and Test Plan (ITP) including Checklists.
The QA/QC Engineer shall maintain a complete master set of approved Inspection and Test Plan
The inspection process shall have the inspection criteria for every Inspection and Test Plan item. Here are the following:

Inspection Responsibilities or Inspection Levels:


Surveillance ( S ) = random attendance at site, no signature  required on the Inspection 

Request ( IR ) or its accompanying documentation.

Execution ( E ) attendance at the site is a must, the signature is always on Inspection Request and Checklist.

Witness (W)  = attendance at the site is expected, the signature is required on check sheet of    Inspection Request ( IR ) and Checklist, but if the signatory is not present to sign at the time, follow on work may proceed and the document(s)  to be singed later.

Hold Point (H) = attendance at the site is mandatory and signature is required on the check sheet of Inspection Request at the time of  the inspection to release the following work.

Review ( R ) = documents to be reviewed, no signature required on the Inspection Request or its accompanying documentation.

Records (RE) = documentation to be recorded, no signature required on the Inspection Request or its accompanying documentation.

Test ( T ) = attendance is required,  signature required on check sheet of Inspection request and checklist.

The main items that need to be specified in an Inspection and Test Plan are :
·         the item that will be checked/inspected/tested (e.g. concrete strength)
·         the document that requires this item to be checked (usually it is the contract or similar document-specification)
·         the document that according to, this item will be inspected/tested (usually a standard or a statutory requirement)
·         the kind of inspection that needs to be performed (visual inspection, document approval etc)
·         the frequency that this inspection needs to be performed (e.g. for concrete slump test = once for every track)
·         the objective criteria/tolerance parameters that will determine if the inspection/test for that item has passed or not
·         the kind of document that will be prepared and saved as a record of pass or failure (usually a signed-off form, a testing machine print-out, a photo etc)
·         if this record needs to be a deliverable, meaning that it needs to be kept and handed over to the Client at the end of the Project as part of the As-Built Folders
·         the responsibilities of every party involved (Contractor, QC Engineer, Client’s Representative etc)

Here is the sample format of the Inspection and Test Plan ( ITP ):

INSPECTION AND TEST PLAN (SAMPLE):

Inspection and Test Plan (ITP), Inspection Records, Inspection Levels, Checklist or QVD Quality Verifying Documents, Preparation, Review and Approval, Inspection Responsibilities, Inspection Levels, Surveillance, Request, Execution, Witness, Hold Point, Test, Review, Records

CHECKLISTS:

Inspection and Test Plan (ITP), Inspection Records, Inspection Levels, Checklist or QVD Quality Verifying Documents, Preparation, Review and Approval, Inspection Responsibilities, Inspection Levels, Surveillance, Request, Execution, Witness, Hold Point, Test, Review, Records


Conclusion:

Full article on Inspection and Test Plan (ITP) | Inspection Records | Inspection Levels Checklist or QVD Quality Verifying Documents | Preparation, Review and Approval Inspection Responsibilities | Inspection Levels Surveillance | Request | Execution | Witness | Hold Point | Test | Review | Records. Thank you for the full reading of this article in "QA QC Civil Engineering" platform in English. If you find this post helpful, then help others by sharing it on social media.

inspection test plan for civil works,inspection test plan for electrical,inspection test plan pdf,inspection test plan for welding and fabrication,inspection test plan for piping,inspection test plan wikipedia,inspection test plan sample download,inspection and test plan for steel structure fabrication,inspection test plan for construction,inspection and test plan for earthworks,inspection and test plan for excavation works,inspection and test plan template concrete,inspection and test plan reinforced concrete,itp civil engineering,inspection and test plan for building construction,itp for excavation and backfilling,inspection test plan sample download,inspection and test plan template concrete,inspection test plan pdf,inspection and test plan for concrete works,inspection and test plan template electrical,inspection test plan for welding and fabrication,What is inspection test plan in construction,What is a hold point inspection,What is an inspection and test plan used for,What is the quality control plan,What is the meaning of ITP in construction,What is a hold point inspection,What is ITP construction,What is the meaning of project quality plan,What is a QA QC plan,What is a control plan in production,What is the meaning of ITP
QA QC Civil Engineering

Hi I am a Civil Engineer by profession but I’ve specialized and taken the journey in the field of Quality Engineering, QA/QC Civil Engineering, Bar Bending Schedule, Quantity Surveying, Construction, Concrete Works, Estimating & Costing and AutoCAD Civil 3D.

Post a Comment

Please Do Not Enter any Spam Link in the Comment Box.

Previous Post Next Post